Hartsdown Park Development Update
By Josh Cole
We are pleased to provide the supporters with an update on the north stand development!
Since February, significant ground works have taken place at the Football Club. Supporters would have seen the large machinery on site across the north stand area, firstly clearing the space, then removing large volumes of soil and setting out the piles.
Despite the fact not much progress is visible above ground, the work on this initial phase was essential for the overall development of the ground, even though it came at significant cost. Works have been completed on schedule and Coniston have left the site across the last week, following completion of this phase.
The two small units left behind the dugouts will be moved in due course, they will not remain there and will be repurposed by the Football Club.
Plans for the next phase are in motion and we will give supporters more information and dates as soon as they are confirmed. When we have news, so will supporters!